Project Overview

Commissioning design phase services included design review, Building Automation System (BAS) sequences of operations review, submittal reviews, coordination meetings, value engineering, RFI coordination, budget control, incorporation of commissioning activities into overall project schedule, and writing Pre-Functional and Functional Test reports.

Commissioning construction phase and acceptance phase services included site visits throughout installations in all 5 phases, including witness of AHU and Chiller startups, review of contractor startup reports, back check of testing and balancing (TAB) in all 5 phases, verification of BAS point-to-point and calibrations, RFI coordination, scheduling, and executing Pre-Functional and Functional Test reports. Issues were tracked via a single comprehensive issues log, reviewed with the project team during frequent project commissioning meetings, and tracked to completion.

Commissioning warranty phase services included review of training agendas, witness of Owner training, review of O&M manuals for commissioned systems and incorporation into Cx Final Report.

Project Location

Port Angeles, Washington

Services Contracted

⦁ HVAC&R
⦁ Chilled Water
⦁ Heating Hot Water
⦁ TAB Back Check & Space Pressurization Verification
⦁ Building Automation System (BAS)
⦁ Disinfectors
⦁ Cart Wash
⦁ Sterilizers
⦁ Compressed Air
⦁ Domestic Hot & Cold Water
⦁ Reverse Osmosis Water
⦁ Steam
⦁ Lighting Control