Case Study

Surgical Suite Steam Humidification VA Hospital Anchorage

Project Overview

Commissioning of renovations to the existing surgical suites at VA Hospital in Anchorage, AK. Building systems renovations were installed and tested so that service to the spaces were continually maintained and operation of medical services were not interrupted.

Commissioning design phase services included design review, Building Automation System (BAS) sequences of operations review, submittal reviews, coordination meetings, value engineering, RFI coordination, budget control, incorporation of commissioning activities into overall project schedule, and writing Pre-Functional and Functional Test reports.

Commissioning construction phase and acceptance phase services included review of contractor startup reports, back check of BAS point-to-point verifications and calibrations, RFI coordination, scheduling, and executing Pre-Functional and Functional Test reports. Issues were tracked via a single comprehensive issues log, reviewed with the project team and tracked to completion. Commissioning warranty phase services included review of training agendas and O&M manuals for commissioned systems and incorporation into Cx Final Report.

Project Location

Anchorage, Alaska

Services Contracted

⦁ HVAC&R
⦁ Heating Hot Water
⦁ Steam
⦁ Electrical Power Distribution
⦁ Building Automation System (BAS)